Project Timeline
Although much of this information is already sprinkled throughout the various sections of the site, I've brought it together here for convenient reference. I've had a little difficulty with some of the earliest dates, although I've put my best guess on work start and work completion, based on what paperwork I have on hand. Some of the projects are listed as "ongoing", which means I sort of picked at them depending upon the weather or supplies available as time permitted. The same is true of projects with overlapping work dates, since I rarely seem to be working on just one thing at a time.
Projects are listed chronologically, and each project is linked to the appropriate sections of the rest of the website for further information.
| 2002 Projects | Work Begun | Work Completed | Notes |
| Septic System Installation | April 2002 | August 2002 | Disposal System Construction Permit: #R14-02 |
| Initial Lot Landscaping | August 2002 | September 2002 | |
| Garden Design & Layout | August 2002 | November 2002 | |
| 2003 Projects | Work Begun | Work Completed | Notes |
| Build Stone Lanterns | April 2003 | August 2003 | |
| Pond Construction | April 2003 | July 2003 | |
| Garden Shed Construction | May 2003 | July 2004 | |
| Irrigation System Installation | May 2003 | August 2003 | |
| 2004 Projects | Work Begun | Work Completed | Notes |
| Additional Garden Plantings | April 2003 | July 2003 | |
| Shoji Door Construction (for shed) | May 2004 | July 2004 | |
| House Renovation Concept Development | September 2004 | Ongoing | |
| Tea House Plans | September 2004 | May 2005 | |
| 2005 Projects | Work Begun | Work Completed | Notes |
| Tea House Construction | May 2005 | August 2005 | |
| Re-frame Porch Windows, Doors and Genkan Floor | September 2005 | December 2005 | |
| Gut and Re-build Utility Room | October 2005 | March 2006 | (installation prep for new boiler & water heater) |
| Install Heat Recovery Ventilator | November 2005 | Ongoing | (some ductwork not yet installed) |
| Create Wiring Schematics | December 2005 | April 2006 | (installation plans for new service panel) |
| 2006 Projects | Work Begun | Work Completed | Notes |
| Install Underfloor Radiant Heat Tubing | February 2006 | November 2009 | |
| Replace All Household Wiring Circuits | March 2006 | Ongoing | |
| Re-build Roof Overhangs and Frame New Entryway Roof | March 2006 | June 2006 | |
| Install New PEX Supply Plumbing | March 2006 | May 2006 | (final plumbing fixture connections occur later) |
| Install New Boiler | April 2006 | April 2006 | |
| Install Indirect Hot Water System | April 2006 | April 2006 | |
| Install New Electrical Service Panel | April 2006 | April 2006 | |
| Strip Old Roof and Install New Roof Shingles | May 2006 | July 2006 | |
| Re-frame Front Window Openings and Install Front Windows | July 2006 | August 2006 | |
| Repair Foundation and Apply Sand Topping Coat | August 2006 | September 2006 | (old porch, Southeast, and South sides) |
| Install Exterior Cement Board Siding | September 2006 | December 2006 | (old porch, Southeast, and South sides) |
| 2007 Projects | Work Begun | Work Completed | Notes |
| Household Wiring Installation Continued | January 2007 | Ongoing | (started working on voice & data wiring too) |
| Underfloor Radiant Heat Tubing Continued | January 2007 | Ongoing | |
| Finish Genkan Walls and Ceilings | January 2007 | June 2007 | |
| Re-mill Old Siding for use in Soffits and Gables | March 2007 | May 2007 | |
| Install Soffit & Gable End Siding | June 2007 | November 2007 | |
| 2008 Projects | Work Begun | Work Completed | Notes |
| Install Whole House Water Filtration | March 2008 | May 2008 | |
| Re-connect Deep Well for Irrigation | April 2008 | June 2008 | |
| Re-frame Rear Window Openings and Install Rear Windows | July 2008 | August 2008 | |
| Re-build Northwest Corner and Install Rear Siding | August 2008 | September 2008 | |
| Apply Sand Topping Coat to Foundation | September 2008 | October 2008 | (West and South sides) |
| Re-build East Kitchen Wall and Floor | September 2008 | October 2008 | |
| Gut Bathroom for Waste and Vent Plumbing | October 2008 | November 2008 | |
| Install New Waste and Vent Plumbing | November 2008 | December 2008 | |
| Install New Shower Unit and Fixtures | November 2008 | December 2008 | |
| 2009 Projects | Work Begun | Work Completed | Notes |
| Re-build and Wire Kitchen Walls and Ceiling | January 2009 | February 2009 | |
| Re-build and Wire Bathroom Walls | February 2009 | March 2009 | |
| Apply Bathroom Wallboard and Finishes | March 2009 | June 2009 | |
| Mill and Install Bathroom Panelling | June 2009 | September 2009 | |
| Paint and Trim Exterior Siding | September 2009 | October 2009 | |
| Underfloor Radiant Heat Tubing Finished | November 2009 | November 2009 | |
| Finish Kitchen Ceiling and Hang Wall Cabinets | November 2009 | November 2009 | |
| Install Kitchen Slate Floor Tile | November 2009 | December 2009 | |
| 2010 Projects | Work Begun | Work Completed | Notes |
| Install Kitchen Base Cabinets | January 2010 | April 2010 | |
| Install Kitchen Mosaic Tile Backsplash | May 2010 | August 2010 | (West wall, behind the stove) |
| Widen Driveway and Re-grade Front Yard | May 2010 | May 2010 | |
| Re-stain and Trim Gable End Siding - Siding Trim Finished | June 2010 | July 2010 | |
| Remove Bedroom Closet and Strip Wall for A/C Install | June 2010 | July 2010 | |
| Install FM / UHF TV Antenna | July 2010 | July 2010 | |
| Create Framing Plan for Engawa & Tsukimi-dai (decks) | July 2010 | August 2010 | |
| Install Remaining Kitchen Mosaic Tile Backsplash | August 2010 | August 2010 | (North wall and area next to pantry) |
| Mill, Finish and Install Kitchen Window Trim | September 2010 | October 2010 | |
| Construct, Apply Laminate and Install Kithen Counter Tops | October 2010 | November 2010 | |
| Kitchen Renovation Completed | December 2010 | February 2011 | (sink install, window treatments, vent duct, etc.) |
| 2011 Projects | Work Begun | Work Completed | Notes |
| Install Standby Power System | Janurary 2011 | February 2011 | |
| Perform Major Site Update | February 2011 | February 2011 | (It takes a while when I blow it off for months...) |
| Install Bathroom Slate Floor Tile | March 2011 | May 2011 | |
| Begin Engawa & Tsukimi-dai Grading Work | June 2011 | July 2011 | |
| Install Bathroom Tile Baseboard & Sealant | July 2011 | July 2011 | |
| Engawa Post & Beam Work | July 2011 | July 2011 | |
| Engawa Roof & Soffit Installation | July 2011 | August 2011 | |
| Engawa & Tsukimi-dai Framing Work & Decking Prep | August 2011 | September 2011 | |
| Tsukimi-dai Landscape Work | September 2011 | October 2011 | |
| Site-wide Code Update | October 2011 | October 2011 | (changes for mobile devices and lightbox) |
| Engawa Decking Prep & Installation | October 2011 | November 2011 | |
| Engawa & Tsukimi-dai Low Voltage Lighting Installation | November 2011 | November 2011 | |
↑